Invoking Arbitration And Other Party's Failure To Act Are Preconditions For Arbitrator Appointment: J&K&L High Court

  • Invoking Arbitration And Other Partys Failure To Act Are Preconditions For Arbitrator Appointment: J&K&L High Court

    The Jammu & Kashmir and Ladakh High Court has recently held that a party seeking appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, must establish that it invoked the arbitration clause and that the other party failed to take steps pursuant to such invocation.

    “The invocation of the arbitration clause by a party and failure on the part of the other party to take steps pursuant to the invocation of the arbitration clause is condition precedent for the Chief Justice or his designate to appoint an arbitrator,” Justice Sanjay Dhar ruled

    The court made the observation while dismissing a contractor's petition seeking appointment of the Chief Engineer, Kashmir PHE (Jal Shakti) Department, Srinagar, as arbitrator in a payment dispute with the Department.

    Although the court found that Clause 16 of the terms and conditions annexed to the allotment order provided for arbitration before the Chief Engineer, the petitioner had failed to produce any material showing that the clause had actually been invoked.

    Background

    The petitioner claimed that the Department had withheld payments despite execution of works at Zadoora, Pulwama, including drilling an exploratory borehole and constructing gravel-packed production tube wells.

    The Department opposed the petition, arguing that the Part-II work had been declared a technical failure due to poor quality, high turbidity and poor yield. It maintained that no technical sanction had been granted, no formal agreement had been executed and the work had neither been completed and tested satisfactorily nor handed over. It also contended that the claim was barred by limitation as no bill had been raised for about four years.

    The Department acknowledged that Part I had been allotted through an order dated October 9, 2019, followed by a formal agreement in March 2021. That work was successfully completed and paid for.

    Court's Observations

    The court rejected the Department's objection that no arbitration clause existed, finding that Clause 16 provided for disputes to be referred to the Chief Engineer.

    However, the communications produced by the petitioner only sought processing and release of bills. They did not contain any request for the appointment of an arbitrator.

    The petitioner's counsel claimed that a legal notice dated September 21, 2024, had been sent seeking appointment of an arbitrator. However, the notice was not placed on record, and the petition did not specifically mention that the arbitration clause had been invoked through it.

    The court also looked at a communication dated December 28, 2024, from the Assistant Executive Engineer to the Executive Engineer, which referred to the legal notice. However, it did not specify who the notice had been addressed to or whether it amounted to invocation of the arbitration clause.

    With no material to establish that the petitioner had invoked the arbitration clause, the court held that it could not appoint an arbitrator and dismissed the petition as not maintainable

    Case Title :  Golden Engineering Bore v. Union Territory of Jammu and KashmirCase Number :  Arb.P No.05/2025CITATION :  2026 LLBiz HC(JAM) 39