REAT
LiveLawBiz RERA Cases Weekly Digest: July 6 - July 11, 2026
NOMINAL INDEXIbrahim Babubhai Chokiya & Ors. v. M/s Westinrely Developers Pvt. Ltd. & Ors., 2026 LLBiz HC(BOM) 377M.P. Real Estate Regulatory Authority v. Shankar Ji Maharaj Trust, 2026 LLBiz HC(MP) 51St. Patricks Realty Private Limited v. Neha Prasad & Ors. and Connected Appeals, 2026 LLBiz REAT(HR) 42Gurcharan Kaur & Another v. Dheeraj Sharma, 2026 LLBiz RERA(PB) 115Anish Charudatta Galgate & Anr. v. Rejoice Homes LLP & Ors., 2026 LLBiz RERA(MH) 116High CourtsBombay...
LiveLawBiz RERA Cases Weekly Digest: June 29 - July 5, 2026
Nominal IndexMacrotech Developers Ltd. v. Suryakant Yashwant Jadhav & Ors., 2026 LLBiz HC(BOM) 358 Emaar India Limited v. Poonam Goel & Ors. and connected matters, 2026 LLBiz REAT(HR) 41 Anil Kumar Kurra v. M/s Adarsh Nivas Pvt. Ltd., 2026 LLBiz RERA(KA) 113 Madhu Mishra v. M/s Redbrick Infrabuild Pvt. Ltd., 2026 LLBiz RERA(BR) 112 Gopishetty Sreenivas v. M/s Suchirindia Infratech Private Limited & Ors., 2026 LLBiz RERA(TS) 114High CourtBombay High CourtPromoter Cannot Use Grace...
Adjudicating Officer Cannot Hear Complaints Seeking Project Development Reliefs: Haryana REAT
The Haryana Real Estate Appellate Tribunal has recently held that an Adjudicating Officer under the Real Estate (Regulation and Development) Act, 2016 cannot entertain complaints seeking directions for development works such as the construction of a boundary wall or roads along with compensation claims. It ruled that such matters fall within the jurisdiction of the Regulatory Authority. The tribunal observed, "The Adjudicating Officer is vested with limited jurisdiction, primarily to...
Limitation Act Doesn't Apply To RERA Complaints: Haryana REAT
The Haryana Real Estate Appellate Tribunal (HREAT) has recently held that complaints filed before the Haryana Real Estate Regulatory Authority cannot be dismissed as time-barred merely because they were filed after possession was handed over. It ruled that the Real Estate (Regulation and Development) Act, 2016 does not prescribe any limitation period for such complaints. The tribunal also held that homebuyers do not lose their right to seek compensation for delayed possession after executing...
LiveLawBiz RERA Half-Yearly Digest: January - June, 2026
Supreme CourtSupreme Court Issues Notice On Plea Alleging Jaypee Used “Facade” Deals To Divert ₹13,833 Crore Homebuyer FundsCase Title: VANDANA SABHARWAL VERSUS UNION OF INDIA & ORS.Case Number: Writ Petition(s)(Civil) No(s).661/2026Citation : 2026 LLBiz SC 213The Supreme Court on Tuesday issued notice on a writ petition alleging that Rs. 13,833 crore out of Rs. 14,599 crore collected from homebuyers by the Jaypee Group was diverted through transfers to group entities and undervalued...
LiveLawBiz RERA Cases Monthly Digest: June 2026
High CourtsMadhya Pradesh High CourtRERA Cannot Demand 25-Year-Old Cooperative Society Records For Project Registration: Madhya Pradesh High CourtCase Title : M.P. Real Estate Regulatory Authority, Bhopal v. Shri Ji Builders and DevelopersCase Number : Writ Appeal No. 2857 of 2024Citation : 2026 LLBiz HC (MP) 47The Madhya Pradesh High Court recently has held that MP-RERA could not reject a real estate project registration application for non-production of a cooperative society's...
LiveLawBiz RERA Cases Weekly Digest: June 22 - June 28, 2026
Nominal IndexM.P. Real Estate Regulatory Authority, Bhopal v. Shri Ji Builders and Developers, 2026 LLBiz HC (MP) 47Kiran Builders Pvt. Ltd. v. Kalpita Enclave Co-operative Housing Society Ltd. & Ors., 2026 LLBiz HC (BOM) 351Rajan Chandiramani v. Swadhinta Builders LLP & Connected Matters, 2026 LLBiz HC (BOM) 355The Army Welfare Housing Organisation (AWHO) & Anr. v. Union of India & Ors. and connected matters, 2026 LLBiz HC (KER) 108Greha Homes Pvt. Ltd. v. Kerala Real Estate...
Virtual Office Spaces Treated As Intangible Property, Fall Outside RERA's Scope: Uttar Pradesh REAT
The Uttar Pradesh Real Estate Appellate Tribunal has held that non-lockable or virtual office spaces fall outside the ambit of the Real Estate (Regulation and Development) Act, 2016. It ruled that the law governs physical real estate units and does not cover such intangible investment interests. The tribunal consequently set aside U.P. RERA's directions requiring Bhutani Group to execute conveyance deeds, hand over possession and pay delay interest. The ruling was delivered by a tribunal...
LiveLawBiz RERA Cases Weekly Digest: June 15 - June 21, 2026
Bombay High CourtBombay High Court Says Homebuyers Retain Right To Delay Interest Despite Staying With ProjectCase Title : CCI Projects Private Limited v. Rajesh Kumar Chaudhary & Ors.Case Number : Second Appeal No. 479 of 2021Citation: 2026 LLBiz HC (BOM) 349The Bombay High Court has held that homebuyers who continue with a housing project despite delayed possession do not lose their statutory right to claim interest for the delay.Justice Sharmila U. Deshmukh dismissed an appeal filed...
Settlement Talks, Vague Legal Advice Can't Justify 299-Day Delay In Filing Appeal: Maharashtra REAT
The Maharashtra Real Estate Appellate Tribunal (REAT) has refused to condone a 299-day delay in an appeal filed by a homebuyer against Acme Industries Private Limited. The tribunal held that claims of settlement talks, conflicting legal advice, and a family bereavement were not enough to justify such a prolonged delay. A coram of Chairperson S.S. Shinde and Member Dr. Rajagopal Devara observed: "The Applicant has neither disclosed the particulars of the alleged advice nor placed any material...
LiveLawBiz RERA Cases Weekly Digest: June 7 - June 13, 2026
Nominal IndexRunwal Constructions v. Bharat Shah & Ors. (Connected Matters), 2026 LLBiz HC (BOM) 310Bangalore Development Authority v. Union of India & Others, 2026 LLBiz HC (KAR) 79N.L. Ravi Shankar & Anr. v. The Registrar, TG Real Estate Regulatory Authority & Ors., 2026 LLBiz REAT (TS) 37M/s. Evos Buildcon Pvt. Ltd. v. Ms. Seema Mohapatra, 2026 LLBiz REAT (OD) 38Sanjeev Kumar Mishra v. Frontier Shelters Pvt. Ltd., 2026 LLBiz RERA (KA) 97Sushila Devi v. M/s Elan Limited, 2026...
Odisha REAT Upholds RERA Order On Shifted Sewage Plant, Finds Ambience Concerns 'Forceful And Logical'
The Odisha Real Estate Appellate Tribunal (OREAT) has recently upheld an Odisha RERA order directing Evos Buildcon Pvt. Ltd. to restore a sewage treatment plant (STP) in its "City Homes" project to the location shown in the sanctioned plan. The tribunal accepted a homebuyer's grievance that the relocation had affected the ambience of her flat. Rejecting the builder's plea that restoring the STP would be costly and affect other residents, the tribunal observed: "The further plea of the...