Developer Cannot Substitute Allotted Plot With Unspecified Alternative Plot: Haryana RERA

  • Developer Cannot Substitute Allotted Plot With Unspecified Alternative Plot: Haryana RERA

    The Haryana Real Estate Regulatory Authority (HRERA), Panchkula, has held that a developer cannot avoid its obligation to deliver an allotted plot by claiming to have offered an alternative without identifying the specific plot, its location, size, and development status.

    Member Chander Shekhar observed that TDI Infrastructure Limited had failed to establish that it had made a concrete alternative offer to a homebuyer who had waited years for possession.

    The Authority held, “In the absence of any definite and concrete alternative allotment, the alleged offer cannot be treated as a valid substitute for the respondent's obligation to hand over the possession of the allotted plot.”

    It further observed that TDI Infrastructure “has severely misused its dominant position” by offering alternative possession in 2018, after a delay of almost ten years, without obtaining an occupation or completion certificate.

    The complaint was filed by Sham Lal Goel over Plot No. J-97B (Corner), measuring 250 square yards, in TDI City, Kundli, Sonipat.

    The plot was initially booked by Anil Mittal on August 21, 2005. Mittal transferred his allotment rights to Chand Gidwani on February 7, 2006. TDI Infrastructure issued an allotment letter to Gidwani on February 12, 2006. Goel acquired the rights on November 1, 2011.

    Despite receiving ₹23,75,659 against the agreed consideration of ₹22,02,812, the developer neither executed a Builder Buyer Agreement nor handed over possession.

    Goel approached HRERA in July 2024, seeking possession of the allotted plot or an alternative plot, along with delay interest.

    TDI Infrastructure argued that the project predated the Real Estate (Regulation and Development) Act, 2016, and had received three part-completion certificates between 2008 and 2017. It also claimed that the complaint was time-barred and that disputes with local landowners had prevented completion of the project.

    The developer relied on a June 5, 2018 communication, which allegedly offered Goel a ready-to-move-in unit in the same project or adjustment of the amount deposited against a unit of his choice in another project.

    Goel denied receiving the communication and pointed out that it did not identify any specific alternative plot.

    Rejecting the objections, HRERA held that TDI Infrastructure had not established that the project obtained a valid completion certificate before May 1, 2017. The fact that the project commenced before RERA came into force did not automatically take it outside the Act's jurisdiction. Part-completion certificates also did not conclusively establish that all development obligations had been fulfilled.

    The Authority rejected the limitation objection, holding that the failure to deliver possession gave rise to a continuing cause of action.

    Since no Builder-Buyer Agreement specified a possession date, HRERA fixed November 1, 2014, three years after Goel acquired the allotment rights, as the deemed possession date.

    It directed TDI Infrastructure to pay ₹31,38,008 in accumulated delay interest up to November 20, 2026, and ₹21,381 per month thereafter until a valid offer of possession is made after obtaining the requisite occupation or completion certificate.

    The prescribed interest rate is 10.95%. The developer was given 90 days to comply. Goel must pay any outstanding agreed consideration upon a valid offer of possession.

    For Complainant (Sham Lal Goel): Advocate Gaurav Gupta.

    For Respondent (TDI Infrastructure Ltd.): Advocates Shubhnit Hans and Samriti.

    Case Title :  Sham Lal Goel v. TDI Infrastructure Ltd.Case Number :  Complaint No. 889 of 2024CITATION :  2026 LLBiz RERA (HR) 167