Delhi High Court Refuses Tata Projects Relief Over Noida Airport's ₹329 Crore Guarantee Encashment

  • Delhi High Court Refuses Tata Projects Relief Over Noida Airports ₹329 Crore Guarantee Encashment

    The Delhi High Court on 26 November declined to grant interim relief to Tata Projects Limited, which sought restitution of Rs. 329.10 crore drawn by Yamuna International Airport Private Limited under three bank guarantees for Phase 1 of Noida International Airport, and also refused to restrain the airport company from invoking two remaining guarantees.

    Justice Tushar Rao Gedela held that encashment of an unconditional bank guarantee does not cause irretrievable injustice warranting interim relief where the amount can be recovered through arbitration. The Bench observed:

    “It cannot be said with conviction or even proposed that the encashment of the BGs, which are purely monetary issues, cannot be restituted by an appropriate legal remedial measure available to the petitioner under the Arbitration Act…”

    The dispute arose from two construction contracts that Yamuna International Airport awarded Tata Projects on 8 June 2022. Valued at Rs. 4,582.02 crore, the contracts covered terminal, airside and landside works, utilities and related infrastructure.

    During execution, Tata Projects raised claims worth Rs. 1,112.87 crore, while the airport company raised counterclaims of Rs. 436.72 crore.

    On 25 February 2026, the parties reached a settlement under which Tata Projects was to receive Rs. 500 crore on agreed terms. They also extended a key construction deadline to 31 July 2026, with a grace period until 29 September.

    Tata Projects failed to meet the extended deadline. Consequently, on 9 October, the airport company encashed two performance guarantees issued by State Bank of India and a Rs. 100 crore advance payment guarantee issued by Union Bank of India. Two guarantees issued by IDBI Bank remained uninvoked.

    Then, Tata Projects approached the High Court under Section 9 of the Arbitration and Conciliation Act, 1996, seeking restitution of the amounts drawn and an injunction against invocation of the remaining guarantees. Alternatively, it sought directions to place the proceeds in escrow or secure them.

    It attributed the delay to the airport company's failure to release the entire first instalment of Rs. 200 crore. It further alleged that the airport company had already recovered the advance payment and had effectively recovered it twice by invoking the guarantee.

    The airport company countered that it had released Rs. 243 crore and that further payments depended on the achievement of contractual milestones. It also maintained that the guarantees were unconditional.

    Justice Gedela held that the dispute over the validity of the guarantee invocations required examination by the Arbitral Tribunal. He said that it “ought to be subject matter of a detailed inquiry by the learned Arbitral Tribunal as and when constituted."

    The Court explained that special equities could justify interim relief on grounds of irretrievable injustice only if the party seeking relief established that no legal or other remedy could recover the money after encashment of the bank guarantee. It said:

    “In other words, while 'irretrievable injustice' may include and subsume all natures of special equities, yet, 'special equities' by themselves may or may not constitute 'irretrievable injustice' in a given case…”

    The Bench further clarified that “...it would be irretrievable injustice when the petitioner decisively establishes a situation where it is impossible for the guarantor to reimburse itself through legal or other remedial measures after the BG has been encashed...”

    Applying this test, it found that Tata Projects had failed to establish irretrievable injustice. Even if its allegations were accepted, it could seek recovery of the amounts encashed through arbitration, including the disputed Rs. 100 crore payment. It added that “none of the actions undertaken by the respondent no.1 render any remedy or restitution, 'irretrievable'.”

    Accordingly, the High Court dismissed the petition, leaving the parties to pursue their contractual claims before the Arbitral Tribunal.

    For Tata Projects Limited: Senior Advocate Rajshekhar Rao, with Advocates Aayush Jain, Arjit Oswal, Yashwant Gaggan and Ajay Sabharwal.

    For Respondents: Senior Advocate Ramji Srinivasan, with Advocates Paritosh Budhiraja, Rajesh Prasad, Kanika Arora, Shefali, Larika Khandelwal, Dishti Sharma, Rishi Raj Deswal, Abhinav Akash and Anuj Maheshwari for Yamuna International Airport Private Limited; Standing Counsel Yash Kotak for State Bank of India; Advocates Vishal Talsania, Nitin Tambwekar and Seshatalpa Sai Bhandaru for IDBI Bank Limited; Advocates O.P. Gaggar and Sachindra Karn for Union Bank of India.

    Case Title :  Tata Projects Limited v. Yamuna International Airport Private Limited & Ors.Case Number :  O.M.P.(I) (COMM.) 478/2026 & I.A. 29182/2026CITATION :  2026 LLBiz HC(BOM) 662