Liquidated Damages Need No Proof Of Actual Loss If It Is Difficult To Quantify: Bombay High Court
Shivani PS
26 Oct 2026 4:11 PM IST

The Bombay High Court on 23 October held that proof of actual loss is not necessary for awarding liquidated damages where the loss is difficult to quantify and the amount stipulated in the contract represents a genuine pre-estimate of damages agreed upon by the parties.
Justice Aarti Sathe dismissed a petition filed by Kumar Urban Development Private Limited under Section 34 of the Arbitration and Conciliation Act, 1996, and upheld an arbitral award directing it to pay Rs. 2.675 crore to The Jal Ratn Deep Co-operative Housing Society Limited for delays in redeveloping 97 residential flats in Mumbai. It observed:
“In cases where damages or loss is difficult to prove, then the liquidated damages amount named in the contract, if it is a genuine pre-estimate of damage or loss agreed between the parties, then in that event the actual damage or loss need not be proved.”
The dispute arose from a redevelopment project involving five residential buildings comprising 97 flats at Bangur Nagar, Goregaon (West), Mumbai.
On 12 January 2011, the society entered into a Development Agreement with Kumar Builders Mumbai Realty Private Limited, which subsequently merged with Kumar Urban Development Private Limited.
Clause 26 of the agreement stipulated liquidated damages of Rs. 10 lakh per week if the developer failed to complete and hand over the redeveloped buildings within the prescribed period and the delay continued beyond 60 days.
Following delays in obtaining municipal approvals and changes in development regulations, the parties executed a fresh Development Agreement on 10 August 2013. However, disputes over the redevelopment obligations persisted, and the project did not progress as contemplated.
On 16 November 2014, the society demanded Rs. 18.80 crore in liquidated damages, following which the developer invoked arbitration.
On 3 March 2017, the sole arbitrator awarded Rs. 6.20 crore in liquidated damages, calculated at Rs. 10 lakh per week for 62 weeks. After adjusting Rs. 1.10 crore towards security deposits and Rs. 2.42 crore towards hardship compensation, the arbitrator determined the net amount payable at Rs. 2.67 crore, along with interest.
Kumar Urban Development challenged the award before the High Court under Section 34 of the Arbitration Act, alleging patent illegality.
The developer argued that Section 74 of the Indian Contract Act, 1872, required proof of loss or legal injury before damages could be awarded. It contended that the society's members had neither vacated their flats nor incurred relocation expenses or suffered displacement. It further argued that the society had benefited from an increase in permissible floor space index and had failed to establish any compensable loss.
The society countered that the contractual rate of Rs. 10 lakh per week represented a genuine pre-estimate of loss and was expressly stipulated as liquidated damages rather than a penalty. It maintained that losses arising from prolonged construction delays were inherently difficult to quantify.
The High Court agreed with the arbitrator that the Development Agreement was in the nature of a construction contract, under which the precise financial consequences of prolonged delays could be difficult to determine.
Referring to the Supreme Court's ruling in Kailash Nath Associates v. Delhi Development Authority, the Court reiterated that actual loss must be proved where it can be established. However, where loss is difficult to quantify, a genuine pre-estimate of damages agreed upon by the parties may be awarded without separate proof of actual loss. It said that “proof of actual loss or damage was not required to be established in the facts of the present case”.
Justice Sathe observed that the arbitrator had examined the contractual provisions and evidence before concluding that the stipulated damages represented a genuine pre-estimate of loss and were not penal in nature.
Further, the Bench held that proceedings under Section 34 do not permit a fresh assessment of evidence merely because another interpretation of the contract is possible. Finding that the award was supported by evidence and suffered from neither patent illegality nor perversity, the Court declined to interfere.
Accordingly, the High Court dismissed Kumar Urban Development's petition and upheld the arbitral award of Rs. 2,67,50,000 with interest. It also directed the release of any amount deposited in Court within one month of the judgment's upload, disposed of pending interim applications and made no order as to costs.
Appearances for petitioner (Kumar Urban Development Private Limited): Senior Advocate Zal Andhyarujina, with Advocates Aditya Shiralkar, Jahaan Dastur, Gaurav Gopal, Mohit Goyal, Shreshtha Sharma and Samyak Jain, instructed by Wadia Ghandy & Co.
Appearances for respondent (The Jal Ratn Deep Co-operative Housing Society Limited): Advocates Rohan Cama, Aman Sadiwala, Yash Dhruva and Siya Ghogare, instructed by MDP Legal.
