The Karnataka Real Estate Regulatory Authority (K-RERA) on 20 November held that the higher market value of a flat at the time of resale must be taken into account while determining the original homebuyers' entitlement to a refund with interest. A developer cannot undervalue the property to defeat their right to recover the amount paid with interest.

Chairman Rakesh Singh partly allowed a complaint filed by two homebuyers against Century Real Estate Holdings Private Limited after the developer failed to hand over their flat within the contractual deadline and subsequently sold it to another buyer, and directed the developer and the subsequent buyer to jointly pay the original homebuyers Rs. 5.75 crore, comprising the amount paid and accrued interest. It observed:

“The higher market value of the property at the time of resale is also to be considered and it cannot be undervalued for the purpose of depriving the right of the complainants for refund with interest...”

Satish Kumar Pandey and Sangeeta Pandey paid Rs. 40 lakh to book two units in Bengaluru's Century Ethos Project on 10 July 2013. They subsequently decided to retain only one flat, C-802, and adjusted the advance paid for the second unit towards its purchase.

On 13 March 2014, they executed sale and construction agreements for Rs. 2,87,98,492. Under the agreements, Century Real Estate Holdings Private Limited was required to hand over possession within 36 months from the issuance of the commencement certificate, with an additional grace period of six months.

The commencement certificate was issued on 20 January 2017, making 20 July 2020 the contractual possession deadline. However, Century failed to deliver the flat within that period.

Discussions regarding a buyback arrangement began in January 2023. The Pandeys alleged that Century failed to honour the timelines it had promised under the arrangement. They consequently withdrew from the resale arrangement on 26 August 2024 and sought registration of the flat in their names.

However, when they visited the project on 25 May 2024, they found that other persons were occupying the flat.

Subsequently, they discovered that Century had already sold the property to Karthik Shankarlingegowda through a sale deed dated 15 May 2024, more than three months before the Pandeys withdrew from the arrangement.

The Pandeys then filed a complaint under Section 31 of the Real Estate (Regulation and Development) Act, 2016, seeking cancellation of the subsequent sale and transfer of the flat to them or, alternatively, a refund. They later dropped their request to reverse the sale and sought a refund with interest, compensation and litigation costs.

On 23 September 2024, the Authority passed an interim order restraining Century from creating any further third-party rights over the flat.

Century attributed the delay in construction to pandemic-related restrictions and pointed out that the project's registration had been extended until 30 September 2022. It also maintained that the Pandeys had consented to the resale arrangement and that it had paid them Rs. 92,81,250 as part payment. It also said that the Pandeys returned this amount on 29 August 2024.

The Authority found that Century had failed to deliver possession within the contractual deadline. It further observed that, having already sold the flat to Karthik, Century could no longer transfer it to the original buyers.

It also held that Sections 18 and 19(4) of the Act entitled the Pandeys to recover the amount paid, along with interest, for the developer's failure to deliver possession in accordance with the agreement.

Moreover, the Bench explained that an allottee can seek a refund, interest and compensation when a promoter fails to hand over possession or violates the agreement for sale. It said:

“Section 19(4) specifies that allottee is entitled to claim refund, interest, and compensation if the promoter fails to deliver possession or violates the agreement for sale...”

The Authority noted that none of the Rs. 2,87,98,492 paid by the Pandeys had been refunded and directed Century and Karthik to pay Rs. 5,74,90,331 within 60 days, including interest at the applicable rates. Further interest would accrue from 20 July 2020 until payment.

Accordingly, the RERA directed the Pandeys to approach the Adjudicating Officer for compensation and permitted enforcement of the order in case of non-compliance. It made no order as to costs.

For the Complainants: Advocate Navya

For the Respondents: Advocate Naveen Kumar

Tags:    
Case Title :  Satish Kumar Pandey and Sangeeta Pandey v. Century Real Estate Holdings Private Limited and Karthik Shankarlingegowda alias Karthik SCase Number :  Complaint No. 00877/2025CITATION :  2026 LLBiz RERA (KA) 165