The Karnataka High Court on 27 October deferred Customs proceedings against Volvo CE India Private Limited concerning the inclusion of royalty and licence fees in the assessable value of imported components, and directed the authorities to consider the company's response in light of a favourable ruling by the Customs, Excise & Service Tax Appellate Tribunal (CESTAT) .

Justice B.M. Shyam Prasad held that Customs authorities must consider a favourable CESTAT ruling in favour of a similarly placed group company before proceeding with an investigation into the inclusion of royalty and licence fees in the assessable value of imported components. The Bench said:

“This Court must also observe that if the Authorities had deferred proceedings under the impugned Inspection Report for over three [3] years because the issue covered under the Inspection Report was being considered by the Tribunal and such issue is answered by the Tribunal in favour of a party who is similarly placed as the petitioner, the reasons that have prevailed with the Tribunal should have been considered same before issuance of the impugned Show Cause…”

Volvo CE India challenged the Special Valuation Branch (SVB) investigation report dated 20 May 2026 and the consequential show cause notice dated 18 August 2026.

The dispute concerned whether royalty and licence fees, calculated at 1.75% of the net sale value of licensed products, could be added to the declared value of imported components, parts and aggregates used in manufacturing those products.

The company submitted that the CESTAT, Bengaluru, had already decided the issue in favour of another group company.

In its order dated 6 May 2026, the Tribunal held that royalty and technical know-how fees could not be added to the transaction value without examining whether the payments were a condition of sale and related to the imported parts used in manufacturing.

It observed that the adjudicating authority had failed to examine the pricing arrangement between the importer and the overseas supplier to determine whether royalty and technical know-how fees were charged as a condition of sale.

Further, the Bench rejected the proposed notional addition of management fees at 4% for the relevant period, observing that the addition was based on assumptions and presumptions, particularly when the importer had discontinued payment of such fees.

Volvo CE India argued that despite submitting the Tribunal's order along with a detailed response on 13 August 2026, the authorities issued the show cause notice without considering the ruling. It also submitted that port authorities were insisting on payment of customs duty in accordance with the investigation report, adversely affecting its business.

The Court observed that although the investigation report was not a final determination, the authorities ought to have considered the Tribunal's findings before issuing the show cause notice. However, it declined to quash the investigation report or the show cause notice at this stage, holding that the adjudicating authority could examine the issue while considering the company's response.

Moreover, it permitted Volvo CE India to submit a detailed reply to the show cause notice, reiterating its earlier response, within four weeks. It said:

“If the Authorities have deferred action pursuant to the Investigation Report because the issue under investigation was being examined by the Tribunal, the proceedings must stand deferred when the petitioner's response is yet to be considered resulting in a final decision…”

The Bench directed the authorities to communicate the deferment of proceedings to port authorities and ensure that no action under the investigation report proceeded while the company's response was under consideration.

It also directed the authorities to grant the company a personal hearing and communicate their decision within three months of receiving its response, leaving all issues open for consideration in light of the Tribunal's observations.

Accordingly, the High Court deferred the Customs proceedings pending consideration of the company's response.

For Petitioner: Advocate Ravi Raghavan, along with Advocates Purvi Asati and Ashwini Nag

For Respondent: Advocate Jeevan J. Neeralgi

Tags:    
Case Title :  M/s Volvo CE India Pvt. Ltd. v. The Commissioner of CustomsCase Number :  WRIT PETITION NO. 32108 OF 2026 (T-CUS)CITATION :  2026 LLBiz HC (KAR) 248