The Delhi High Court has recently ruled that an arbitral tribunal cannot award a contractor additional payment for excess material consumption without identifying a contractual provision or an independent legal basis for doing so.

This is particularly so when the contractor has not raised a claim on the basis of quantum meruit.

Justice Om Prakash Shukla observed, “the Respondent's claim was not based on quantum meruit, nor was any such case was pleaded before the Tribunal. The Tribunal was, therefore, required to identify a contractual provision or some other legal basis for awarding additional payment but none of it was relied upon by the learned Tribunal.”

The court partially set aside two arbitral awards in favour of B.G. Shirke Constructions Technology Private Limited against the Delhi Development Authority (DDA). The dispute concerned additional payment claimed for excess cement consumption in M-30 grade concrete.

The dispute arose from two contracts awarded by the DDA to the construction company for building LIG and EWS houses in Narela and Rohini, Delhi.

The contractor claimed that it had quoted its rates based on cement consumption of 330 kg per cubic metre. The DDA, however, instructed it to use 410 kg per cubic metre.

The arbitral tribunal held that the minimum cement content for M-30 grade concrete was 330 kg per cubic metre. It awarded ₹3,16,78,614 to the contractor for excess cement consumption up to June 30, 2015.

The tribunal also directed the DDA to pay Rs. 6 per kg for excess cement consumed from July 1, 2015 onwards. It further ordered the refund of amounts recovered for cement consumption below 410 kg per cubic metre in M-30 grade concrete.

The court found that the tribunal had not established how the additional cement consumption created a separate payment obligation under the contract. The agreement was a lump-sum contract, and the requirement to use 410 kg of cement per cubic metre fell within the prescribed range of 330 kg to 500 kg under the CPWD Specifications.

The court also pointed out that the contractor had not pleaded a claim under quantum meruit. Even if the additional cement was used on the DDA's instructions, the tribunal had to examine whether those instructions entitled the contractor to additional payment under the agreement.

It also had to consider whether the instructions amounted to a variation of the contracted work carrying such an entitlement. The award did not identify any such contractual provision or explain how the additional consumption became separately payable.

“It is a settled position of law that an Arbitral Tribunal is a creature of the contract and must operate strictly within its four corners. While the construction of contractual terms falls within the domain of the Tribunal, it cannot, under the guise of interpretation, rewrite the contract or invent a payment mechanism where none exists. It is well settled an award that ignores express contractual stipulations or re-writes the contract suffers from patent illegality under Section 34 of the Act,” the court observed.

The court further noted that the tribunal had taken a recovery rate meant for deficient cement consumption and applied it in reverse. This effectively created a payment entitlement for excess consumption.

Clause 1.12 prescribed a recovery rate of Rs. 6 per kg for deficient cement consumption. However, it did not provide for payment at the same rate when consumption exceeded the prescribed quantity.

“The absence of a right to recover an amount from the Contractor does not, by itself, create a corresponding right in the Contractor to claim payment,” the court observed.

The court separately examined the contractual provisions governing cement consumption. Clause 9.1.2 specifically referred to M-25 and M-35 grade concrete, while Clause 9.1.3 prescribed a minimum cement content of 360 kg per cubic metre for “any grade of RCC”.

The latter provision also covered M-30 grade concrete. The court held that there was no ambiguity between the two clauses concerning M-30 that warranted applying the principle of contra proferentem.

The tribunal had overlooked the specific reference to “any grade of RCC” in Clause 9.1.3. It had mechanically extended its finding of inconsistency between the two clauses to M-30, without examining the specific requirement applicable to that grade.

The court clarified that it found no ground to interfere with the tribunal's interpretation of the contractual provisions concerning M-25 and M-35 grade concrete.

Accordingly, the court set aside the awards to the extent they treated 330 kg per cubic metre as the minimum cement content for M-30 grade concrete. It also set aside the award of ₹3,16,78,614, the direction for further payments at ₹6 per kg, and consequential refunds to the extent they were based on the erroneous payment entitlement, along with consequential interest.

The remaining findings of the arbitral tribunal were left undisturbed.

For Petitioner: Advocates Chand Chopra and Punishk Handa, Sanjay Katyal

For Respondent: Advocates Rajiv Kapoor and Ashit Kapoor with Ashok Patil in person.

Tags:    
Case Title :  Delhi Development Authority v. B.G. Shirke Constructions Technology private LimitedCase Number :  O.M.P. (COMM) 361 and 362/2017 & I.A. 11448 and 11451 of 2017CITATION :  2026 LLBiz HC (DEL) 1282