The National Company Law Appellate Tribunal (NCLAT) at Delhi has held that the pendency of arbitration does not automatically prevent a creditor from initiating insolvency proceedings under Section 7 of the Insolvency and Bankruptcy Code (IBC).

However, it said the debt and default must be established independently of unresolved contractual disputes.

“The pendency of arbitration, by itself, does not automatically bar proceedings under Section 7 of the Code. The question, however, is whether the financial debt and default relied upon for admission are sufficiently clear and established independently of the unresolved contractual issues,” the Tribunal observed.

The NCLAT made the observation while staying further insolvency proceedings against ESPO Developers Private Limited, finding that the existence of debt and default, as on the date of filing the insolvency application, was “not free from substantial doubt”.

A Bench of Judicial Member Justice Sharad Kumar Sharma and Technical Members Arun Baroka and Indevar Pandey passed the order on November 25.

The appeals were filed by Balbir Singh, suspended director of ESPO Developers, challenging the NCLT's September 29 order admitting a Section 7 petition filed by Omkara Assets Reconstruction Private Limited. A second appeal challenged the rejection of the corporate debtor's application under Section 65 of the IBC.

The dispute began with a ₹135.15 crore loan given to ESPO Developers in 2019. After an OTS letter in 2021, the parties signed a Settlement Agreement in March 2023 covering the loan and property transactions. Singh said the obligations were linked and the original loan could be revived only through a valid termination. Omkara claimed it had validly terminated the agreement in July 2024. The dispute is now before an arbitral tribunal, where Omkara has filed a counterclaim

The appellate tribunal noted that the alleged revival of the original loan liability “depends substantially upon the validity and effect of the termination of the Settlement Agreement”.

Since the termination itself was disputed and pending consideration in arbitration, the Tribunal said the matter required closer examination.

It also observed that insolvency jurisdiction “is not intended to be used as a substitute for adjudication of disputed contractual claims or as a means of recovery”.

Granting interim relief, the NCLAT noted that Omkara could pursue its counterclaim in arbitration. However, allowing the insolvency process to continue could cause consequences for ESPO Developers that might not be capable of being adequately undone if Singh ultimately succeeded in the appeals.

The Tribunal stayed further proceedings arising from the NCLT's admission order, including further steps in the corporate insolvency resolution process, until its next order.

It clarified that arbitration could continue and that its observations were confined to interim relief and would not determine the parties' final rights and liabilities.

For Appellants: Senior Advocate Virender Ganda with Advocates Vishal Ganda, Riya Palnitkar, Pulkit Goyal and Pratham Sharma

For Respondents: Senior Advocates Gopal Jain and Gaurav Mitra, with Advocates Meghna Mishra, Yashodhara Gupta,Kevin Chadha and Yash Singh

Tags:    
Case Title :  Balbir Singh Vs Omkara Assets Reconstruction Private Limited & OrsCase Number :  Company Appeal (AT) (Insolvency) 1966/2026 & 2017/2026CITATION :  2026 LLBiz NCLAT 451