The Supreme Court on Monday orally remarked that excessive procedural wrangling was one of the biggest hurdles facing arbitration, observing that parties should not allow disputes over procedural issues to overshadow the arbitral process.
“This is where arbitration is suffering its biggest hurdle. Too much of procedural wranglings,” Justice Joymalya Bagchi remarked while hearing Delhi Airport Metro Express Private Limited's (DAMEPL) challenge to a Delhi High Court ruling that London was the juridical seat of arbitration in its dispute with Spanish company Construcciones y Auxiliar de Ferrocarriles (CAF).
A Bench of Chief Justice Surya Kant and Justices Joymalya Bagchi and V. Mohana made the observation after DAMEPL's counsel repeatedly sought to draw a distinction between the law governing the parties' contractual obligations and the procedural law governing the arbitration.
The dispute concerned two agreements between DAMEPL and CAF that provided for arbitration under the International Chamber of Commerce (ICC) Rules, with London designated as the seat or place of arbitration. While the agreements contained references to Indian law, DAMEPL sought to highlight the implications of those references for determining the law governing the arbitral proceedings.
During the hearing, counsel appearing for DAMEPL referred to paragraphs 143 and 151 of the impugned judgment and submitted that the central question concerned the relationship between the law governing the contractual obligations and the procedural law governing arbitration.
Justice Bagchi observed that the choice of London as the place of arbitration, read with the ICC Rules, indicated the parties' intention to have the arbitral proceedings governed by the procedural framework under those rules.
"Procedural law of ICC will apply and in this situation we find no reason to apply the Indian law.... ICC rules will apply. Even if there is some reference in a allied contract with regard to Indian law, the overwhelming intention of parties is to be governed by ICC procedural laws," Justice Bagchi observed.
Counsel, however, continued to press the argument concerning references to Indian law in the related contractual provisions, seeking to preserve the question concerning the interplay between the governing law of the contracts and the procedural law governing arbitration.
It was in this context that Justice Bagchi remarked that excessive procedural wrangling was one of arbitration's biggest hurdles.
Counsel thereafter sought permission to withdraw the challenge, requesting that the legal question concerning the relationship between the juridical seat and the governing law of the contract be left open.
The court, however, dismissed the special leave petition, finding no ground to interfere with the High Court's judgment
Background
The parties had entered into a Rolling Stock Supply Contract and a Maintenance Services Agreement (MSA) on June 30, 2008, providing for arbitration under the International Chamber of Commerce (ICC) Rules, with London designated as the seat or place of arbitration.
Disputes arose after DAMEPL encashed a performance bank guarantee worth €4.76 million, alleging that CAF had failed to meet contractual specifications. CAF initiated arbitration in London, where the majority of the arbitral tribunal directed DAMEPL to refund the amount, holding that it had failed to establish actual financial loss justifying its retention.
DAMEPL challenged the arbitral awards under Section 34 of the Arbitration and Conciliation Act, 1996, before the Delhi High Court. A Single Judge dismissed the petition, holding that London was the juridical seat of arbitration and Part I of the Act was inapplicable. DAMEPL subsequently challenged this decision before a Division Bench under Section 37 of the Act, arguing, among other things, that Indian courts had jurisdiction because Indian law governed the contracts.
The Division Bench of Justices C. Hari Shankar and Om Prakash Shukla dismissed the appeal, holding that London was the juridical seat of arbitration and that the parties' choice of the ICC Rules, read with the contractual provisions, demonstrated their intention to exclude Part I of the Indian Arbitration Act.