Delhi HC Dismisses Wadia Appeals, Refuses Higher Consultancy Fees In Married Accommodation Project Dispute

Update: 2026-03-24 11:11 GMT

The Delhi High Court on Tuesday dismissed appeals filed by Wadia Techno Engineering Services Limited challenging arbitral awards in disputes arising from consultancy agreements for defence housing projects, holding that the consultant was not entitled to higher fees or compensation for delays.

The court upheld a single judge's order refusing to interfere with the arbitral awards while maintaining the limited setting aside of certain claims relating to the Vizag project.

A Division Bench of Justice Anil Kshetrapal and Justice Amit Mahajan observed,

In the present case, the Tribunal has examined the contractual definition of “Project Cost” (Article 1.9), the structure of consultancy fees (Article 1.10), and the absence of any clause providing for escalation of consultancy fees. The conclusion reached by the Tribunal that the consultancy fee was not subject to revision merely because the cost of the project increased during execution cannot be said to be an interpretation that is implausible or contrary to the contract.

The dispute traces back to consultancy agreements entered into between Wadia Techno Engineering Services Limited and the Director General of the Married Accommodation Project for construction works at Visakhapatnam, Pune, and Ahmednagar.

Under these contracts, Wadia was to provide design, supervision, and project management services, for which it was paid consultancy charges worked out as a fixed percentage of the project cost. The execution of the projects, however, did not proceed as planned. Timelines stretched, and in the Pune and Ahmednagar works the original contractors had to be terminated, with the balance work later awarded through risk-and-cost tenders. The change in execution pushed up the overall cost of the projects and became the basis of Wadia's claim for higher fees.

Wadia claimed that the rise in project cost and prolonged timelines entitled it to higher consultancy fees and additional compensation, while the Director General of Married Accommodation Project argued that the contract fixed the fee and barred any extra payment except where specifically provided.

Arbitral tribunals rejected the claims in awards dated August 17, 2023, which were later challenged before the High Court. A Single Judge set aside the award only in respect of certain fee-related claims in the Vizag project but upheld the awards in all other respects.

Before the Division Bench, Wadia argued that consultancy fees linked to “project cost” should automatically increase when project costs rose, and that extended timelines required continued deployment of staff.

Rejecting the contention, the Court held that the agreements did not provide for automatic escalation of consultancy fees and specifically limited payment in cases involving risk-and-cost contracts.

On claims for prolongation costs, the Court relied on contractual clauses stating that delays would not have any financial effect on the consultancy agreement and noted that Wadia had not produced sufficient evidence of additional expenditure.

"The Tribunal has examined the contractual clauses governing extension of the project period and has concluded that the extensions granted in the present case did not carry any financial consequences. Such an interpretation of the contractual provisions falls squarely within the domain of the Arbitral Tribunal," the bench held.

The court reiterated that under Sections 34 and 37 of the Arbitration and Conciliation Act, courts cannot re-appreciate evidence or substitute their own interpretation where the arbitral tribunal has taken a plausible view.

Holding that no patent illegality or perversity was shown, the court dismissed the appeals, while leaving the parties free to pursue fresh arbitration on the limited Vizag claims that had earlier been set aside.

For Appellant (Wadia Techno Engineering Services Limited): Advocates Ashok Singh, Anirudh Sanganeria, Himanshu Raj, Pragati Singh, Rajat Joshi, Esha Garg.

For Respondents (Director General of Married Accommodation Project & Anr.): Advocates Ripudaman Bharadwaj, Kushagra Kumar, Amit Kumar Rana, Pragati Trivedi, Arnav Kumar, Manya Gupta.

Tags:    
Case Title :  Wadia Techno Engineering Services Limited v. Director General of Married Accommodation Project & Anr.Case Number :  FAO(OS) (COMM) 195/2024 & connected mattersCITATION :  2026 LLBiz HC (DEL) 297

Similar News